We checked every dated launch and delivery promise in our robot tracker against what shipped. Robot vacuums and mowers mostly arrive when promised. Humanoids and home robots mostly don't.
Kept on time, by kind of robot
Promises that fell due, by kind. Appliances mostly keep their dates; humanoids and home robots mostly do not.
- On time
- Late
- Not arrived yet
Show as a table
| Type of robot | On time | Late | Not yet | Total |
|---|---|---|---|---|
| Cleaning, mowing and pool robots | 9 | 3 | 1 | 13 |
| Home, companion and care robots | 2 | 8 | 16 | 26 |
| Humanoids | 1 | 1 | 8 | 10 |
Every robot that missed its first ship date
Every robot in our tracker that missed its first promised delivery date, the longest delay first. The table runs from the date the maker first promised to the day the robot shipped, or to today if it hasn’t.
| Robot | First promised | Shipped, or today | Months late |
|---|---|---|---|
| JennieTombot | Aug 2020 | Not shipped as of 26 Nov 2026 | 76 |
| S3WYBOT | Q2 2025 | Not shipped as of 26 Nov 2026 | 17 |
| Fourier GR-3Fourier | Oct 2025 | Not shipped as of 26 Nov 2026 | 13 |
| OptimusTesla | 2025 | Not shipped as of 26 Nov 2026 | 12 |
| ApolloApptronik | 2025 | Not shipped as of 26 Nov 2026 | 11 |
| PhoenixSanctuary AI | 2025 | Not shipped as of 26 Nov 2026 | 11 |
| Unitree H2Unitree Robotics | Apr 2026 | Not shipped as of 26 Nov 2026 | 7 |
| AgiBot A2 (Yuanzheng A2)AgiBot | Oct 2024 | 16 Dec 2024 | 2 |
| YUKAMammotion | 20 May 2024 | 9 Jun 2024 | 1 |
Robot makers kept 12 of 49 dated delivery promises on time: 24.5%. These are promises to put a robot on sale or deliver it by a stated date, made at least a month ahead, whose date has now passed. Another 12 were kept late. The remaining 25 are still unmet, a median of 14 months after the date.
The gap between home robot promises and reality depends on what is being promised. Makers of robot vacuums, mowers and pool robots kept 9 of 13 promises. Humanoid makers kept 1 of 10, and makers of home, companion and care robots kept 2 of 26.
Key facts
- Data: 350 dated public promises about 143 robots, from 237 robots tracked; 202 (58%) rest on the maker's own words. Snapshot and outcomes as of 23 November 2026.
- Scored: 49 forward sale or delivery promises that have fallen due: 12 kept on time (24.5%), 12 late, 25 still unmet.
- Delay: median 10.7 months for missed promises; 17 of 37 missed promises are a year or more late.
- Humanoids: 1 of 10 kept. 28 more humanoid promises are not yet due, most by the end of 2027.
- Demos: 8 of 19 live humanoid demos (42%) were remote-controlled.
- Checked twice: a second rater scored every promise blind and agreed on 98.2% (Cohen's kappa 0.98).
- Updated: 23 Nov 2026
!Kept on time, kept late and still unmet, by type of robot
Five findings
- Fewer than 1 in 4 promises were kept on time. Of 49 dated sale or delivery promises made at least a month ahead that have now fallen due, 12 (24.5%) were met by the date.
- Appliance makers deliver and humanoid makers mostly don't. Makers of robot vacuums, mowers and pool robots kept 9 of 13 promises (69%). Humanoid makers kept 1 of 10, and makers of home, companion and care robots 2 of 26.
- A missed promise runs almost a year late. The median delay was 10.7 months at the cut-off, and 17 of the 37 missed promises are a year or more late.
- Tombot's Jennie robot puppy has kept its buyers waiting longest, with 9 missed delivery dates on record. Its first promised date, May 2020, is 77.7 months past, and the puppy is still on a waitlist.
- A person was at the controls for 8 of 19 humanoid abilities shown live in public (42%). Another 119 of 167 recorded humanoid abilities have only been claimed, never shown.
The headline numbers
| What we measured | Result |
|---|---|
| Dated promises in the tracker | 350, about 143 robots |
| From the maker's own words (primary source) | 202 (58%) |
| Forward promises (made at least 30 days before the date) | 198 |
| Forward sale or delivery promises that have fallen due and can be judged | 49, from 32 robots and 27 makers |
| Kept on time | 12 (24.5%) |
| Kept late | 12 (median 3.6 months late) |
| Still unmet | 25 (median 14.0 months overdue) |
| Not yet due | 34 |
| Outcome not judgeable (on sale, but no sale date known; or discontinued without delivery) | 42 |
A promise counts as kept when the robot was on sale or delivered to paying customers, in any market, by the end of the period the maker named. "Late 2025" means by 31 December 2025, "summer 2025" by 22 September 2025, and "2026-Q1" by 31 March 2026. Pre-orders, deposits, waitlists and pilots don't count. The full rules are published with the data.
By type of robot
| Robot group | Judged | Kept on time | Late | Still unmet | Median miss (months) |
|---|---|---|---|---|---|
| Robot vacuums, mowers, pool and window robots | 13 | 9 (69.2%) | 3 | 1 | 2.4 |
| Humanoid robots (home, research, industrial) | 10 | 1 (10.0%) | 1 | 8 | 10.7 |
| Home, companion and care robots | 26 | 2 (7.7%) | 8 | 16 | 15.4 |
| All | 49 | 12 (24.5%) | 12 | 25 | 10.7 |
Median miss covers late and still-unmet promises together. Source: RobotScore tracker, 23 November 2026.
Appliance makers mostly announce a product when it is ready and name a day a few weeks away. Humanoid and home-robot makers announce a year or more ahead, and those dates slip. Most humanoid promises can't be judged yet, because 28 are not yet due. They come from Tesla Optimus, 1X NEO, Boston Dynamics Atlas, Apptronik Apollo, XPeng IRON and others, and most fall due on 31 December 2026 or during 2027.
!Months late, for promises kept late and still unmet
Promises that fell due in 2025 and 2026
Between 1 January 2025 and 23 November 2026, 26 promises for 22 robots reached their deadline. 9 were kept, 2 were kept late and 15 are still unmet.
The kept ones are almost all robot vacuums and mowers with a fixed launch day: the Roborock Saros 10 and Saros 20, the Dreame X50 Ultra, the iRobot Roomba Max 705, the MOVA Z70, the Ecovacs GOAT O800, the Mammotion LUBA mini AWD and the Segway Navimow X390. One humanoid made the list. The Unitree R1 went on spot sale on 24 June 2026, six days before its 30 June date.
The unmet ones read like a list of the most talked-about robots of the period. Tesla Optimus missed two promises of units for outside customers in 2025. Samsung Ballie missed H1 2025 and summer 2025, Tombot Jennie missed 2025 and then Q1 2026, LG's Q9 home robot missed 2025 and Weave Isaac missed fall 2025. Apptronik Apollo, Sanctuary Phoenix, Fourier GR-3, Hugging Face HopeJR and Unitree H2 are on the same list.
The biggest misses
!The slip chart: each robot's biggest miss
| Robot | Promise (said on) | Deadline | Outcome on 23 Nov 2026 | Months late |
|---|---|---|---|---|
| Tombot Jennie | May 2020, Kickstarter first-edition reward (5 Mar 2019) | 31 May 2020 | still on a waitlist | 77.7, still open |
| Cozmo 2.0 (Digital Dream Labs) | spring 2021 (17 Dec 2020) | 20 Jun 2021 | never delivered (pre-order) | 65.1, still open |
| 1X EVE | late 2022, via ADT (22 Mar 2022) | 31 Dec 2022 | pilot only | 46.7, still open |
| ElliQ | 2018 (8 Jan 2018) | 31 Dec 2018 | on sale from 15 Mar 2022 | 38.5 |
| Samsung Ballie | 2024 (8 Jan 2024) | 31 Dec 2024 | never sold | 22.7, still open |
| Jibo | fall 2015 (16 Jul 2014) | 20 Dec 2015 | shipped Nov 2017; later discontinued | 22.4 |
| Wybot S3 pool robot | shipments Q2 2025 (6 Jan 2025) | 30 Jun 2025 | pre-order | 16.8, still open |
| Fourier GR-3 | October 2025 deliveries (8 Sep 2025) | 31 Oct 2025 | pre-order | 12.7, still open |
| Weave Isaac | fall 2025 (2024) | 20 Dec 2025 | pre-order | 11.1, still open |
| Tesla Optimus | units shipped to outside customers in 2025 (24 Jan 2024) | 31 Dec 2025 | no outside delivery recorded | 10.7, still open |
Each robot's biggest miss among forward promises. "Still open" means the delay is still growing. Every source is in the dataset.
Tesla Optimus: 34 dated promises
Tesla Optimus has more dated promises on record than any other robot: 34 since 2021. 25 of them come from Tesla's own words in earnings calls, shareholder letters and SEC filings. Most are about production, which can't be checked from outside, so we don't score them.
Two promises to put Optimus in outside hands have passed. On the Q4 2023 call (24 January 2024) the line was "I think we've got a good chance of shipping some number of Optimus units next year". On the Q1 2024 call (23 April 2024) it was "I think we may be able to sell it externally by the end of next year".
Neither had happened by 23 November 2026. Tesla's Q3 2026 shareholder letter says Optimus production began in Fremont. On the Q3 2026 call, on 21 October 2026, the date given for delivering Optimus to companies outside Tesla was late 2027.
!Tesla Optimus: every dated promise
!The robots with the most dated promises
Who delivers to homes
The tracker has 237 robots. Their status on 23 November 2026, by group:
| Group | On sale | Pre-order | Pilot | Prototype | Discontinued |
|---|---|---|---|---|---|
| Robot vacuums, mowers, pool and window robots (145) | 134 | 2 | 0 | 0 | 9 |
| Home, companion and care robots (47) | 32 | 5 | 1 | 5 | 4 |
| Humanoid robots (45) | 19 | 7 | 10 | 5 | 4 |
For humanoids, "on sale" mostly means research and education robots, or industrial robots sold to companies. Very few are robots for homes.
Of the five humanoids built for homes, one is on sale: Noetix Bumi, a small education humanoid sold only in China. No delivery date is recorded for it. The other four have no recorded delivery to a home buyer. 1X NEO, Clone Alpha and Zeroth Bridge are on pre-order, and Figure 03 is in a pilot. 1X's order page still says "US Deliveries start 2026", and that promise falls due on 31 December 2026.
Demos with a person at the controls
!Evidence behind humanoid abilities
Our tracker records how each claimed ability has been shown. Of 167 humanoid abilities, 11 were shown live and autonomous. Another 8 were shown live but teleoperated, which means a person in another place was steering the robot remotely. A further 29 appear only in the maker's own videos, and 119 have only been claimed.
So 8 of the 19 live demos (42%) were remote-controlled. Teleoperation is a fair way to train and demonstrate a robot. Buyers should still know which kind of demo they are watching.
Prices that rose and fell
Nine robots have a comparable recorded price change: same market, same kind of price, earliest to latest. Five got cheaper, all of them robots already on sale or sold. The Ecovacs Deebot X9 Pro Omni fell by −50.0%, Moxie by −46.7%, the Dreame A2 in Germany by −28.6%, the Ecovacs Deebot X11 by −26.7% and the Unitree R1 by −25.1%.
Four got dearer, and the biggest rise belongs to a robot nobody can buy yet. Tombot Jennie rose +401.7% while still on a waitlist: $299 was quoted in 2019, against about $1,500 reported in 2025–26. Tombot says that is not yet a final price. temi rose +166.8% and the eufy E15 mower +12.6%. LOVOT 3.0 has a rise of +8.3% announced for mid-January 2027.
What you can buy where you live
We counted robots on sale now that list the country or have a local price there. The US has 92 tracked robots, 19 of them home, companion or care robots or humanoids. Japan has 51, including 13 home and companion robots, most of them made in Japan. Germany, Austria and Switzerland have 57, but only 2 home robots. France and Belgium have 25, Italy 19, Spain 17 and Korea 18. Brazil and Portugal have 2.
Outside the US and Japan, a "home robot" mostly means a vacuum or a mower.
Kept and missed: the extremes
Roborock kept every dated promise we could score, 2 of 2. Ecovacs, iRobot, MOVA, Narwal, Segway Navimow and Sony (aibo, 2018) kept 1 of 1 each.
The most missed promises sit with a handful of makers:
| Maker | Robot | Missed | What happened |
|---|---|---|---|
| Tombot | Jennie | 9 unmet | First promised for May 2020; still on a waitlist |
| Embodied | Moxie | 4 late | Promised for September to fall 2020; first shipped March 2021; later discontinued |
| Samsung | Ballie | 3 unmet | 2024, H1 2025, summer 2025; never sold |
| Tesla | Optimus | 2 unmet | Outside units in 2025, and external sales by the end of 2025 |
| 1X | EVE | 2 unmet | Offered through ADT for late 2022, then late 2023; still a pilot |
| Intuition Robotics | ElliQ | 2 late | Promised for 2018, then summer 2019; on sale from March 2022 |
Facts only, from dated sources. Before publication we asked every maker named in the slip chart for comment; replies are added here as received.
Does the result hold?
!On-time rate under different scoring rules
We re-ran the headline seven ways:
- primary sources only: 20.8% of 24;
- excluding robots sold only in China: 25.5% of 47;
- excluding appliances: 8.3% of 36;
- with a 30-day grace period: 28.6% of 49;
- including production promises: 19.4% of 67;
- only promises about global or unspecified markets: 6.7% of 15;
- all dated promises, including same-day "on sale today" launches: 60.6% of 109.
In six of seven alternative scorings the on-time rate stays between 6.7% and 28.6%. It only climbs above half when we count same-day "on sale today" launches, which cannot be missed.
A second, independent rater applied the published rules to all 350 promises without seeing our results. Both raters agreed on 98.2% of the 340 distinct promises (Cohen's kappa 0.98). All six disagreements concern promises outside the headline, with wording such as "available now" or "soon".
What this means if you are buying
A robot vacuum, mower or pool robot with a launch date a few weeks away will most likely arrive on time. A humanoid or home robot with a date a year or more away probably won't. On our numbers, fewer than 1 in 10 such promises was kept on time, and a miss typically runs to about a year.
My advice is to treat any date from a humanoid or home-robot maker as a hope rather than a plan, and to spend accordingly. Read the refund terms before you pay a deposit: Cozmo 2.0 pre-orders were never delivered. And ask whether a demo was autonomous, since two in five live humanoid demos in our records were remote-controlled.
Each robot's dates are on its tracker page in Help at home, and the full timeline is in Promised vs shipped: every home robot delivery date, tracked.
Method
The data is every dated public promise in the RobotScore tracker that a robot would be on sale, delivered, in production, available to pre-order or unveiled. Each promise has its own dated source. For the robots journalists ask about most, we rebuilt the history from the first announcement: Tesla Optimus, 1X NEO and EVE, Figure, Samsung Ballie, Amazon Astro, LG's home robots, Tombot Jennie, Moxie, ElliQ, Loona, Unitree R1, Weave Isaac, Sunday Memo, and the Mammotion and Segway Navimow mowers.
Every promise is tagged by source. Primary means the maker's own release, blog, keynote, filing or earnings call; secondary means a press report. Apple's rumoured home robot is left out because there is no official statement. The snapshot was taken on 23 November 2026, and outcomes are judged as of the same day.
Only sale and delivery promises are scored. We leave out unveilings, pre-orders and production starts, promises made after a robot had already shipped somewhere, and promises with no readable date. One statement covering several markets with the same date counts once. The headline uses forward promises, meaning those made at least 30 days before the date.
The deadline is the last day of the named period. For a month, quarter, half-year or year, that is its last day. "Late" or "end of" means 31 December, "early" means 30 April and "mid" means 31 August. Spring ends on 20 June, summer on 22 September and fall on 20 December, while Christmas is 25 December. A range ends with its later part.
A robot counts as delivered from the earliest of its recorded first delivery to paying customers and, if it is on sale, the date it went on sale, in any market. This favours makers, because a US launch counts even when the promise was about Europe.
For late promises, the delay is the months from the deadline to delivery. For unmet promises, it runs from the deadline to 23 November 2026, which makes it a minimum: the delay is still growing.
The method has limits. The tracker holds the promises we found and could source, which is short of every promise ever made. Small groups can swing on a single robot. And 42 promises can't be judged because a robot is on sale but we have no date for when it went on sale.
All 350 promises, with sources, deadlines, both raters' results and every summary number, are free to download and reuse with credit, together with the full scoring rules. Found a promise we missed or a wrong date? Send us the source.
This report replaces the first version published on 23 November 2026, which covered 202 promises. The direction is the same, and the on-time rate moved from 27.9% to 24.5%. The first version also said that robots waiting to ship got dearer while robots on sale got cheaper. That was wrong: temi, the eufy E15 and LOVOT 3.0 rose while on sale.
Appendix: the 49 judged promises
Every forward sale or delivery promise that had fallen due by 23 November 2026, with its source. "Months" is the delay at the cut-off: final for late promises, a minimum for unmet ones. All 350 promises are in the dataset.
| Robot | Maker | Said on | Promised | Deadline | Outcome | Months | Source |
|---|---|---|---|---|---|---|---|
| AgiBot A2 (Yuanzheng A2) | AgiBot | 2024-08-19 | 2024-10 (small-scale production and first deliveries) | 2024-10-31 | Late (delivered 2024-12-16) | 1.5 | secondary |
| aibo ERS-1000 | Sony | 2017-11-01 | 2018-01-11 | 2018-01-11 | Kept | secondary | |
| Apollo | Apptronik | 2025-02-13 | 2025 | 2025-12-31 | Still unmet | 10.7 | primary |
| Ballie | Samsung Electronics | 2024-01-08 | 2024 | 2024-12-31 | Still unmet | 22.7 | secondary |
| Ballie | Samsung Electronics | 2025-01-06 | 2025-H1 | 2025-06-30 | Still unmet | 16.8 | secondary |
| Ballie | Samsung Electronics | 2025-04-09 | summer 2025 | 2025-09-22 | Still unmet | 14.0 | primary |
| Cozmo 2.0 | Digital Dream Labs | 2020-12-17 | spring 2021 | 2021-06-20 | Still unmet | 65.1 | primary |
| ElliQ | Intuition Robotics | 2018-01-08 | 2018 | 2018-12-31 | Late (delivered 2022-03-15) | 38.5 | primary |
| ElliQ | Intuition Robotics | 2019-01-07 | summer 2019 | 2019-09-22 | Late (delivered 2022-03-15) | 29.8 | primary |
| EVE | 1X Technologies | 2022-03-22 | late 2022 | 2022-12-31 | Still unmet | 46.7 | primary |
| EVE | 1X Technologies | 2023-01-05 | late 2023 | 2023-12-31 | Still unmet | 34.7 | secondary |
| Fourier GR-3 | Fourier | 2025-09-08 | 2025-10 (official launch and start of deliveries) | 2025-10-31 | Still unmet | 12.7 | secondary |
| Freo Z Ultra | Narwal | 2024-09-06 | 2024-10-08 | 2024-10-08 | Kept | primary | |
| GOAT O800 RTK | ECOVACS Robotics | 2025-01-10 | 2025-02-10 | 2025-02-10 | Kept | secondary | |
| HopeJR | Hugging Face / The Robot Studio | 2025-05-29 | end of 2025 (first few units) | 2025-12-31 | Still unmet | 10.7 | secondary |
| Isaac 1 | Weave Robotics | 2024 | fall 2025 | 2025-12-20 | Still unmet | 11.1 | primary |
| Jennie | Tombot | 2019-03-05 | 2020-08 (Kickstarter puppy rewards from $149) | 2020-08-31 | Still unmet | 74.7 | primary |
| Jennie | Tombot | 2019-03-05 | 2020-05 (Kickstarter Exclusive / First Edition puppy rewards) | 2020-05-31 | Still unmet | 77.7 | primary |
| Jennie | Tombot | 2020-11-19 | 2022 | 2022-12-31 | Still unmet | 46.7 | secondary |
| Jennie | Tombot | 2021-10-22 | fall 2023 (1,000 units shipped) | 2023-12-20 | Still unmet | 35.1 | primary |
| Jennie | Tombot | 2022-09-28 | 2024 | 2024-12-31 | Still unmet | 22.7 | primary |
| Jennie | Tombot | 2023-05-31 | 2024 | 2024-12-31 | Still unmet | 22.7 | primary |
| Jennie | Tombot | 2024-10-31 | 2025 | 2025-12-31 | Still unmet | 10.7 | primary |
| Jennie | Tombot | 2024-12-05 | 2025 | 2025-12-31 | Still unmet | 10.7 | secondary |
| Jennie | Tombot | 2025-06-17 | 2026-Q1 | 2026-03-31 | Still unmet | 7.7 | secondary |
| Jibo | Jibo, Inc. | 2014-07-16 | fall 2015 | 2015-12-20 | Late (delivered 2017-11-01) | 22.4 | secondary |
| Jibo | Jibo, Inc. | 2016-11-20 | 2017 | 2017-12-31 | Kept | secondary | |
| L50 Ultra | Dreame Technology | 2025-01-15 | 2025-02 | 2025-02-28 | Late (delivered 2025-07-08) | 4.3 | secondary |
| LG Q9 (Smart Home AI Agent) | LG Electronics | 2025-01-24 | 2025 | 2025-12-31 | Still unmet | 10.7 | primary |
| LUBA mini AWD | Mammotion | 2025-01-08 | from early March 2025 | 2025-03-31 | Kept | secondary | |
| Moxie | Embodied, Inc. | 2020-04-28 | 2020-10 (goal of 'shipping robots to everyone by October') | 2020-10-31 | Late (delivered 2021-03-01) | 4.0 | secondary |
| Moxie | Embodied, Inc. | 2020-05-04 | fall 2020 | 2020-12-20 | Late (delivered 2021-03-01) | 2.4 | secondary |
| Moxie | Embodied, Inc. | 2020-05-04 | 2020-09 | 2020-09-30 | Late (delivered 2021-03-01) | 5.0 | secondary |
| Moxie | Embodied, Inc. | 2020-08-30 | fall 2020 | 2020-12-20 | Late (delivered 2021-03-01) | 2.4 | primary |
| Navimow X390 | Segway Navimow | 2025-01-07 | spring 2025 | 2025-06-20 | Kept | primary | |
| Optimus | Tesla | 2024-01-24 | 2025 | 2025-12-31 | Still unmet | 10.7 | primary |
| Optimus | Tesla | 2024-04-23 | late 2025 | 2025-12-31 | Still unmet | 10.7 | primary |
| Pepper | SoftBank Robotics | 2014-06-05 | 2015-02 | 2015-02-28 | Late (delivered 2015-06-01) | 3.1 | primary |
| Phoenix | Sanctuary AI | 2024-04-12 | 2025 (all Phoenix production runs deployed into Magna manufacturing facilities over the next year) | 2025-12-31 | Still unmet | 10.7 | secondary |
| Roomba Max 705 Combo Robot + AutoWash Dock | iRobot | 2025-07-22 | later in 2025 | 2025-12-31 | Kept | primary | |
| S3 | WYBOT | 2025-01-06 | 2025-Q2 (shipments) | 2025-06-30 | Still unmet | 16.8 | secondary |
| Saros 10 | Roborock | 2025-01-05 | 2025-02-10 | 2025-02-10 | Kept | primary | |
| Saros 20 | Roborock | 2026-01-06 | 2026-Q2 | 2026-06-30 | Kept | secondary | |
| Unitree H2 | Unitree Robotics | 2026-02-13 | 2026-04 (phased deliveries start) | 2026-04-30 | Still unmet | 6.8 | secondary |
| Unitree R1 | Unitree Robotics | 2026-04-10 | 2026-06-30 | 2026-06-30 | Kept | secondary | |
| X50 Ultra Complete | Dreame Technology | 2025-01-06 | 2025-02-14 | 2025-02-14 | Kept | primary | |
| X60 Max Ultra Complete | Dreame Technology | 2026-01-06 | 2026-02-10 | 2026-02-10 | Late (delivered 2026-02-11) | 0.0 | primary |
| YUKA | Mammotion | 2024-03-13 | 2024-05-20 (Kickstarter early backers) | 2024-05-20 | Late (delivered 2024-06-09) | 0.6 | secondary |
| Z70 Ultra Roller Complete | MOVA | 2026-04-15 | 2026-06-23 | 2026-06-23 | Kept | secondary |
Robots in this article

Tesla, industrial humanoid · Prototype
Not announced
1X Technologies, home humanoid · Pre-order
$20,000 or $499 a month
1X Technologies, industrial humanoid · Pilot
Not announced
Figure AI, home humanoid · Pilot
Not announced
Samsung Electronics, wheeled home robot · Prototype
Not announced
Tombot, care robot · Pre-order
$1,500
Digital Dream Labs, desk companion · Pre-order
$399.99
Intuition Robotics, care robot
$249 + $49 a month
Sources
- Tesla (TSLA) Q1 2024 earnings call transcript
- Tesla (TSLA) Q4 2023 earnings call transcript
- Transcript: Tesla Q3 2026 earnings call
- Samsung and Google Cloud expand partnership, bring Gemini to Ballie
- Order NEO
- Tombot - Affordable Robotic Companion Animals for Seniors (Kickstarter; reward estimates read from a Wayback capture of 2019-03-19)